Willow International Phase I - Food Service/Bookstore

Project Status

Date Posted: 7/24/2008 8:00:00 AM

Willow International Phase I – Foodservice / Bookstore
Measure E Budget:
$2,814,258
Total Expenses to Date:
$2,616,303
Balance:
$197,955

Construction is complete and both phases of the project were accepted at the April Board meeting. This project will no longer be detailed in future reports.

Date Posted: 7/30/2007 8:00:00 AM

Willow International Phase I – Foodservice / Bookstore
Measure E Budget:
$2,814,258
Total Expenses to Date:
$211,249
Balance:
$2,603,009

The project has been bid and awarded at the May 2007 Board meeting. Site work is in progress in preparation for the delivery of the portable units September 2007.