Date Posted: 7/24/2008 8:00:00 AM

Willow International Phase II
Measure E Budget:
$18,739,000
Total Expenses to Date:
$1,768,667
Balance: $16,970,33

The project was out to bid in April and awarded at the June Board meeting.The contractor has mobilized and earthwork has begun.

Date Posted: 7/30/2007 8:00:00 AM

Willow International Phase II
Measure E Budget:
$19,276,000
Total Expenses to Date:
$1,444,203
Balance: $17,831,797

Working Drawings were submitted to DSA by the Architect late June 2007. Review by DSA is expected to be complete by January 2008, with construction beginning Spring 2008.

Date Posted: 4/26/2007 8:00:00 AM

Preliminary Plans have been approved by the State Chancellor’s Office and the District is authorized to proceed with Working Drawings.

Date Posted: 1/22/2007 8:00:00 AM

With the passage of State Proposition 1D this project is funded 50% State and 50% Measure E. The total budget for this project is $38,523,000. Preliminary Plans are in progress.

Date Posted: 7/18/2006 8:00:00 AM

Project Title: Willow/International Phase II

Funding Source: Measure E / State*

Project Description: Phase II of the new Willow International Community College Center will consist of a 50,000 sq. ft. Academic Building housing student services office, library and library services, data processing, science labs, nursing labs, physical education, distance learning, lecture hall, classrooms, faculty and administrative offices and meeting rooms.

Anticipated Completion Date: 2010

Status: The District’s Final Project Proposal (FPP) was submitted to the State Chancellor’s Office in July 2004 and was approved in September 2005. State has increased allocation to projects by 30% to adjust for inflation thus increasing the District’s match obligation. Darden Architects has been authorized to proceed with Preliminary Plans.

Estimated Project Budget: Prepared by Edwin S. Darden Associates

Funding Source: Measure E / State*

* Construction is dependent upon authorization and passage of State Bond in 2006.

ONSITE WORK

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

2,429,000

88,066

0

0

0

88,066

Consultant Services

637,000

0

0

0

0

0

Fees & Other Charges

520,000

4,013

0

0

0

4,013

Construction & Equipment

32,766,919

0

0

0

0

0

Inspection & Testing

581,000

0

0

0

0

0

Contingency

1,519,000

0

0

0

0

0

Total

38,452,919

92,079

0

0

0

92,079


Date Posted: 5/1/2006 8:00:00 AM

Project Title: Willow/International Phase II

Funding Source: Measure E / State*

Project Description: Phase II of the new Willow International Community College Center will consist of a 50,000 sq. ft. Academic Building housing student services office, library and library services, data processing, science labs, nursing labs, physical education, distance learning, lecture hall, classrooms, faculty and administrative offices and meeting rooms.

Anticipated Completion Date: 2010

Status: The District’s Final Project Proposal (FPP) was submitted to the State Chancellor’s Office in July 2004 and was approved in September 2005. State has increased allocation to projects by 30% to adjust for inflation thus increasing the District’s match obligation. Darden Architects has been authorized to proceed with Preliminary Plans.

Estimated Project Budget: Prepared by Edwin S. Darden Associates

Funding Source: Measure E / State*

* Construction is dependent upon authorization and passage of State Bond in 2006.

ONSITE WORK

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

1,640,000

88,066

0

0

0

88,066

Consultant Services

431,000

0

0

0

0

0

Fees & Other Charges

410,000

4,013

0

0

0

4,013

Construction & Equipment

24,264,919

0

0

0

0

0

Inspection & Testing

505,000

0

0

0

0

0

Contingency

1,025,000

0

0

0

0

0

Total

28,275,919

92,079

0

0

0

92,079


Date Posted: 11/4/2005 3:10:00 PM

Funding Source: Measure E / State*

Project Description: Phase II of the new Willow International Community College Center will consist of a 50,000 sq. ft. Academic Building housing student services office, library and library services, data processing, science labs, nursing labs, physical education, distance learning, lecture hall, classrooms, faculty and administrative offices and meeting rooms.

Anticipated Completion Date: 2010

Status: The District submitted and received approval by the State Chancellor’s Office Summer 2003 of the IPP that defined the parameters of the project. The District’s Final Project Proposal (FPP) which further defines the project was submitted, along with preliminary site and building schematic drawings, to the State Chancellor’s Office for approval Summer 2004. State has increased allocation to projects by 5% to adjust for inflation.

Estimated Project Budget: Prepared by Edwin S. Darden Associates

Funding Source: Measure E / State*

* Construction is dependent upon authorization and passage of State Bond in 2006 and/or 2008

ONSITE WORK

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

1,640,000

63,938

0

0

0

63,938

Consultant Services

431,000

0

0

0

0

0

Fees & Other Charges

410,000

4,013

0

0

0

4,013

Construction & Equipment

24,264,919

0

0

0

0

0

Inspection & Testing

505,000

0

0

0

0

0

Contingency

1,025,000

0

0

0

0

0

Total

28,275,919

67,951

0

0

0

67,951


Date Posted: 11/4/2005 2:58:00 PM

Funding Source: Measure E / State*

Project Description: Phase II of the new Willow International Community College Center will consist of a 50,000 sq. ft. Academic Building housing student services office, library and library services, data processing, science labs, nursing labs, physical education, distance learning, lecture hall, classrooms, faculty and administrative offices and meeting rooms.

Anticipated Completion Date: 2010

Status: The District submitted and received approval by the State Chancellor’s Office Summer 2003 of the IPP that defined the parameters of the project. The District’s Final Project Proposal (FPP) which further defines the project was submitted, along with preliminary site and building schematic drawings, to the State Chancellor’s Office for approval Summer 2004. State has increased allocation to projects by 5% to adjust for inflation.

Estimated Project Budget: Prepared by Edwin S. Darden Associates

Funding Source: Measure E / State*

* Construction is dependent upon authorization and passage of State Bond in 2006 and/or 2008

ONSITE WORK

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

1,640,000

63,938

0

0

0

63,938

Consultant Services

431,000

0

0

0

0

0

Fees & Other Charges

410,000

4,013

0

0

0

4,013

Construction & Equipment

24,264,919

0

0

0

0

0

Inspection & Testing

505,000

0

0

0

0

0

Contingency

1,025,000

0

0

0

0

0

Total

28,275,919

67,951

0

0

0

67,951


Date Posted: 8/19/2005 12:59:00 PM

Funding Source: Measure E / State*

Project Description: Phase II of the new Willow International Community College Center will consist of a 50,000 sq. ft. Academic Building housing student services office, library and library services, data processing, science labs, nursing labs, physical education, distance learning, lecture hall, classrooms, faculty and administrative offices and meeting rooms.

Anticipated Completion Date: 2010

Status: The District submitted and received approval by the State Chancellor’s Office Summer 2003 of the IPP that defined the parameters of the project.The District’s Final Project Proposal (FPP) which further defines the project was submitted, along with preliminary site and building schematic drawings, to the State Chancellor’s Office for approval Summer 2004.

Estimated Project Budget: Prepared by Edwin S. Darden Associates

Funding Source: Measure E / State*

* Construction is dependent upon authorization and passage of State Bond in 2006 and/or 2008

ONSITE WORK

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

1,640,000

63,938

0

0

0

63,938

Consultant Services

431,000

0

0

0

0

0

Fees & Other Charges

410,000

4,013

0

0

0

4,013

Construction & Equipment

22,905,000

0

0

0

0

0

Inspection & Testing

505,000

0

0

0

0

0

Contingency

1,025,000

0

0

0

0

0

Total

26,916,000

67,951

0

0

0

67,951


Date Posted: 4/22/2005 1:39:00 PM

The District submitted and received approval by the State Chancellor’s Office Summer 2003 of the IPP that defined the parameters of the project. The District’s Final Project Proposal (FPP) which further defines the project was submitted, along with preliminary site and building schematic drawings, to the State Chancellor’s Office for approval Summer 2004.

Date Posted: 1/18/2005 9:21:00 AM

The District submitted and received approval by the State Chancellor’s Office Summer 2003 of the IPP that defined the parameters of the project. The District’s Final Project Proposal (FPP) which further defines the project was submitted, along with preliminary site and building schematic drawings, to the State Chancellor’s Office for approval Summer 2004.

Date Posted: 4/5/2004 2:52:00 PM

The State Chancellor’s Office has approved the District’s Initial Project Proposal (IPP). The District will be presenting a Final Project Proposal (FPP) for approval at the April Board meeting. Upon Board approval, the District will submit the FPP to the State Chancellor’s Office by July 1, 2004.

Date Posted: 3/3/2004 8:25:00 AM

The District has presented an Initial Project Proposal (IPP) to the State Chancellor’s Office in June 2003 for approval. The State Chancellor’s Office has not approved any IPPs from the 2003 submissions statewide. The District’s architect, Edwin S. Darden Associates is under contract and will have completed the next phase of the state’s funding program, called the Final Project Proposal (FPP), for submission to the state in May 2003.

Date Posted: 10/16/2003 12:49:00 PM

The SCCCD Board of Trustees at its June 24 meeting selected and authorized the administration to enter into an agreement with Edwin S. Darden Associates, Inc., as the project architects. The administration is in contract negotiations with Edwin S. Darden Associates, Inc.