Measure E: Our community colleges...putting the Valley to work.

Home

Project Information

Fresno City College

Parking Study and Expansion

Project Status

Date Posted: 7/30/2007 8:00:00 AM

Measure E Budget: $2,631,200
Total Expenses to Date: $35,789
Balance: $2,595,411

A preliminary parking study has been developed by District’s consultant in conjunction with District’s facilities department and FCC staff. The project will proceed as part of the OAB campus utilization and EIR study.

Date Posted: 1/22/2007 8:00:00 AM

A preliminary parking study has been developed by District’s consultant in conjunction with District’s facilities department and FCC staff. The project will proceed as part of the OAB campus utilization and EIR study.

Date Posted: 7/18/2006 8:00:00 AM

Project Title: FCC Parking Study and Expansion
Funding Source: Measure E

Project Description: Expansion of parking facilities for the FCC campus.

Anticipated Completion Date: Fall 2009

Status: A preliminary parking study has been developed by District’s consultant in conjunction with District’s facilities department and FCC staff. The project will proceed as part of the OAB campus utilization and EIR study.

Estimated Project Budget: Prepared by Kitchell - Program Manager

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

171,539

22,083

0

0

0

22,083

Consultant Services

64,327

0

0

0

0

0

Fees & Other Charges

38,446

0

10,000

1,903

0

1,903

Construction & Equipment

2,144,234

0

0

0

0

0

Inspection & Testing

105,442

0

0

0

0

0

Contingency

107,212

0

0

0

0

0

Total

2,631,200

22,083

10,000

1,903

0

23,986


Date Posted: 5/1/2006 8:00:00 AM

Project Title: FCC Parking Study and Expansion
Funding Source: Measure E

Project Description: Expansion of parking facilities for the FCC campus.

Anticipated Completion Date: Fall 2009

Status: A preliminary parking study has been developed by District’s consultant in conjunction with District’s facilities department and FCC staff. The project will proceed as part of the OAB campus utilization and EIR study.

Estimated Project Budget: Prepared by Kitchell - Program Manager

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

171,539
22,083
0
0
0
22,083

Consultant Services

64,327
0
0
0
0
0

Fees & Other Charges

38,446
0
10,000
1,903
0
1,903

Construction & Equipment

2,144,234
0
0
0
0
0

Inspection & Testing

105,442
0
0
0
0
0

Contingency

107,212
0
0
0
0
0

Total

2,631,200
22,083
10,000
1,903
0
23,986

Date Posted: 11/4/2005 2:24:00 PM

Funding Source: Measure E

Project Description: Expansion of parking facilities for the FCC campus.

Anticipated Completion Date: Fall 2009

Status: A preliminary parking study has been developed by District’s consultant in conjunction with District’s facilities department and FCC staff. The project will proceed as part of the OAB campus utilization and EIR study.

Estimated Project Budget: Prepared by Kitchell - Program Manager

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

171,539
22,083
0
0
0
22,083

Consultant Services

64,327
0
0
0
0
0

Fees & Other Charges

38,446
0
10,000
0
0
0

Construction & Equipment

2,144,234
0
0
0
0
0

Inspection & Testing

105,442
0
0
0
0
0

Contingency

107,212
0
0
0
0
0

Total

2,631,200
22,083
10,000
0
0
22,083

Date Posted: 8/19/2005 9:50:00 AM

Project Description: Expansion of parking facilities for the FCC campus.

Anticipated Completion Date: 2009

Status: A preliminary parking study has been developed by District’s consultant in conjunction with District’s facilities department and FCC staff. The project will proceed as part of the OAB campus utilization and EIR study.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

171,539

22,083

0

0

0

22,083

Consultant Services

64,327

0

0

0

0

0

Fees & Other Charges

38,446

0

10,000

0

0

0

Construction & Equipment

2,144,234

0

0

0

0

0

Inspection & Testing

105,442

0

0

0

0

0

Contingency

107,212

0

0

0

0

0

Total

2,631,200

22,083

10,000

0

0

22,083


Date Posted: 4/22/2005 1:36:00 PM

A preliminary parking study has been developed by District’s consultant in conjunction with District’s facilities department and FCC staff. The project will proceed as part of the OAB campus utilization study.

Date Posted: 1/18/2005 9:14:00 AM

A preliminary parking study has been developed by District’s consultant in conjunction with District’s facilities department and FCC staff. The project will proceed as part of the OAB campus utilization study.

Date Posted: 4/5/2004 2:53:00 PM

A parking study has been reviewed by District and FCC staff. Further action on this project is contingent upon the completion of the Environmental Impact Report for the Old Administration Building.

Date Posted: 3/3/2004 8:34:00 AM

The site selection study has been reviewed by District and FCC staffs. Additional direction has been provided to the consultant to develop cost estimates for selected expansion options.

Date Posted: 10/16/2003 12:49:00 PM

The SCCCD Board of Trustees at its September 2 meeting selected and authorized the administration to enter into an agreement with Blair, Church & Flynn Consulting Engineers for the development of a parking study and expansion of parking and FCC. The study is currently under development and review by staff.