Before:

Project Status

Date Posted: 7/30/2007 8:00:00 AM

Reedley College Residence Hall
Measure E Budget:
$8,970,000
Total Expenses to Date:
$291,908
Balance:
$8,678,092

Design development is in progress. Drawings are scheduled to be submitted to DSA Fall 2007 and anticipated to be received back Winter 2008. The bidding and construction process is scheduled to start Summer 2008.

Date Posted: 4/26/2007 8:00:00 AM

Preliminary Plans are complete and Working Drawings are in progress. Working Drawings are anticipated to be complete and submitted to DSA during Summer 2007.

Date Posted: 1/22/2007 8:00:00 AM

The Board approved NTD/STICHLER as the project architect at the May 3, 2005 meeting. The design is being value engineered to bring project within budget.

Date Posted: 7/18/2006 8:00:00 AM

Project Title: Reedley College Student Residence Hall

Funding Source: Measure E

Project Description: A new Residence Hall building with 100 rooms for 200 students including common and recreation areas to replace the existing 35-year old facility.

Anticipated Completion Date: 2008

Status: The Board approved NTD/STICHLER as the project architect at the May 3, 2005 meeting. The design is being value engineered to bring project within budget.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

397,060

0

52,368

52,368

0

52,368

Consultant Services

148,898

6,840

11,554

11,554

0

18,394

Fees & Other Charges

88,991

126

0

0

0

126

Construction & Equipment

4,963,255

0

0

0

0

0

Inspection & Testing

133,633

0

0

0

0

0

Contingency

248,163

0

0

0

0

0

Total

5,980,000

6,966

63,922

63,922

0

70,888


Date Posted: 5/1/2006 8:00:00 AM

Project Title: Reedley College Student Residence Hall

Funding Source: Measure E

Project Description: A new Residence Hall building with 100 rooms for 200 students including common and recreation areas to replace the existing 35-year old facility.

Anticipated Completion Date: 2007

Status: The Board approved NTD/STICHLER as the project architect at the May 3, 2005 meeting. NTD/STICHLER has met with District and Campus planning committees and programming, schematic design, and preliminary plans are completed.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

397,060

0

375,000

52,368

0

52,368

Consultant Services

148,898

6,840

24,700

6,880

1,040

13,720

Fees & Other Charges

88,991

126

300

0

0

126

Construction & Equipment

4,963,255

0

0

0

0

0

Inspection & Testing

133,633

0

0

0

0

0

Contingency

248,163

0

0

0

0

0

Total

5,980,000

6,966

400,000

59,248

1,040

66,214


Date Posted: 11/4/2005 3:20:00 PM

Funding Source: Measure E

Project Description: A new Residence Hall building with 100 rooms for 200 students including common and recreation areas to replace the existing 35-year old facility.

Anticipated Completion Date: 2007

Status: The Board approved NTD/STICHLER as the project architect at the May 3, 2005 meeting. NTD/STICHLER has met with District and Campus planning committees and programming and schematic design are in progress.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

397,060

0

375,000

8,400

366,400

8,400

Consultant Services

148,898

5,800

24,700

260

21,600

6,060

Fees & Other Charges

88,991

126

300

0

0

126

Construction & Equipment

4,963,255

0

0

0

0

0

Inspection & Testing

133,633

0

0

0

0

0

Contingency

248,163

0

0

0

0

0

Total

5,980,000

5,926

400,000

8,660

388,000

14,586


Date Posted: 8/19/2005 1:36:00 PM

Funding Source: Measure E

Project Description: A new Residence Hall building with 100 rooms for 200 students including common and recreation areas to replace the existing 35-year old facility.

Anticipated Completion Date: 2007

Status: The Board approved NTD/STICHLER as the project architect at the May 3, 2005 meeting.NTD/STICHLER has met with District and Campus planning committees and programming and schematic design are in progress.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

397,060

0

175,000

0

0

0

Consultant Services

148,898

5,800

24,700

0

0

5,800

Fees & Other Charges

88,991

126

300

0

0

126

Construction & Equipment

4,963,255

0

0

0

0

0

Inspection & Testing

133,633

0

0

0

0

0

Contingency

248,163

0

0

0

0

0

Total

5,980,000

5,926

200,000

0

0

5,926


Date Posted: 4/22/2005 1:42:00 PM

Architect approval by Board is scheduled for May 3, 2005. Programming and schematic design will begin Spring semester of 2005.

Date Posted: 1/18/2005 9:32:00 AM

Architect approval by Board is scheduled for February 1, 2005. Programming and schematic design will begin Spring semester of 2005.